SW Cogen Ceramics CHP Case Study

Project:
5.6MW Ceramics CHP Project, UAE

Technology:
Taurus 60 Gas Turbine

Highlights:

  • CHP Plant for one of the largest Ceramic Manufacturing Plant in UAE
  • Plant designed 122F ambient temperature and high atmospheric dust
  • Retrofit of Gas Turbine, 160m of ducting routing and 30 m Chimney installed
  • Project delivered in 12 Months and is achieving 85% Cogeneration Efficiency